Submittal 4
Consent of surety to release of retainage at Substantial Completion
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
- Specification section
- 00 6
- Type
- Certificate
- Status
- Not yet submitted
Description
Specification 00 6 Agreement Between Owner and Contractor for Construction Contract (stipulated Price), paragraph Article 6.04 A. Owner will not return or release retainage at Substantial Completion or any other time unless Contractor submits written consent of the surety to such return or release. Closeout.
Disposition
☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only