Submittal 25
Consent of surety to final payment
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
- Specification section
- 00 13
- Type
- Certificate
- Status
- Not yet submitted
Description
Specification 00 13 Standard General Conditions of the Construction Contract, paragraph Article 15.06 A.2.b. The final Application for Payment must be accompanied by consent of the surety to final payment (Agreement Article 6.04 A also requires surety consent before final payment is made). Closeout.
Disposition
☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only