CBY Airport Water Extension

Submittal 25

Consent of surety to final payment
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
00 13
Type
Certificate
Status
Not yet submitted

Description

Specification 00 13 Standard General Conditions of the Construction Contract, paragraph Article 15.06 A.2.b. The final Application for Payment must be accompanied by consent of the surety to final payment (Agreement Article 6.04 A also requires surety consent before final payment is made). Closeout.

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History

Printed Oct 12, 2026, 8:55 AM by VisitorWorkhorse · Hesiod Holdings