CBY Airport Water Extension

Submittal 59

Action and informational submittals required by individual Specification Sections (general requirement)
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
01 33 00
Type
Other
Status
Not yet submitted

Description

Specification 01 33 00 Submittal Procedures, paragraph 1.06 A. Prepare and submit the Product Data, Shop Drawings, Samples, qualification data, certificates, and test reports called for in each Section as PDF packages uploaded to PDC Sharefile under the Section with email notice to karen.brady@respec.com, all items for a Section concurrently, action and informational submittals under separate transmittals, allowing 5 days for each review and resubmittal (1.05 D, 1.06 B, 1.06 C, 1.07). During construction.

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History

Printed Oct 12, 2026, 8:57 AM by VisitorWorkhorse · Hesiod Holdings