CBY Airport Water Extension

Submittal 11

Progress Schedule, preliminary
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
00 13
Type
Schedule
Status
Not yet submitted

Description

Specification 00 13 Standard General Conditions of the Construction Contract, paragraph Article 2.03 A.1. Within 10 days after the Effective Date of the Contract, submit to Engineer a preliminary Progress Schedule indicating times for starting and completing the stages of the Work including Milestones; reviewed at the schedules conference at least 10 days before the first Application for Payment (Article 2.05).

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History