Submittal 818
PCS training schedule
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
- Specification section
- 40 60 00
- Type
- Schedule
- Status
- Not yet submitted
Description
Specification 40 60 00 Process Control System, paragraph 3.26 C.1. Schedule training with Owner 20 business days before expected Substantial Completion and give at least 10 business days' notice; minimum two days total in no more than two classes of at least two consecutive days, all before the end of the warranty period. Closeout.
Disposition
☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only