CBY Airport Water Extension

Submittal 636

Dewatering work plan
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
31 23 19
Type
Work plan
Status
Not yet submitted

Description

Specification 31 23 19 Dewatering, paragraph 1.04 A.1. Submit the Dewatering Work Plan within 30 calendar days after notice to proceed, prepared per the current ADEC Division of Water Quality BMP Plan Template; allow 14 calendar days for review, and no site work other than inspections and surveys until approved (3.02 A, C); keep an approved copy at the onsite office and update as conditions change (3.03 C).

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History

Printed Oct 12, 2026, 8:55 AM by VisitorWorkhorse · Hesiod Holdings