Submittal 811
PCS validation test plan and pretest checklist
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
- Specification section
- 40 60 00
- Type
- Work plan
- Status
- Not yet submitted
Description
Specification 40 60 00 Process Control System, paragraph 3.22 E. Submit the Pretest Checklist and Test Plan before validation testing, 10 business days before start of tests; the plan addresses all Attachment A control sequences, simulation methods, expected results, and a step-by-step test checklist. During construction.
Disposition
☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only