CBY Airport Water Extension

Submittal 54

Construction schedule, initial (Gantt chart)
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
01 32 00
Type
Schedule
Status
Not yet submitted

Description

Specification 01 32 00 Construction Progress Documentation, paragraph 2.02 A. Submit a comprehensive, fully developed horizontal Gantt-chart construction schedule within 10 days of the date established for the Notice of Award; format per 1.03 A is a working electronic schedule file (Microsoft Project), a PDF, and two paper copies.

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History

Printed Oct 12, 2026, 8:55 AM by VisitorWorkhorse · Hesiod Holdings