38 Schedule of values
Details
- Specification section
- 01 29 00
- Type
- Schedule
- Priority
- Normal
- Description
- Specification 01 29 00 Payment Procedures, paragraph 1.04 A.2. Submit to Engineer through the Owner's Project Manager at the earliest possible date but no later than seven days before the initial Application for Payment, in EJCDC C-620 format with at least one line item per Specification Section, separate stored-materials and purchase-contract lines, and closeout line items totaling five percent of the Contract Sum (1.04 B).