53 Recovery schedule
Details
- Specification section
- 01 32 00
- Type
- Schedule
- Priority
- Low
- Description
- Specification 01 32 00 Construction Progress Documentation, paragraph 2.01 F. When a periodic update shows the Work 14 or more calendar days behind the current approved schedule, submit a separate recovery schedule indicating the means by which Contractor intends to regain compliance. During construction. Read from the section with medium confidence; confirm the requirement before sending.