629 Excavation and trenching plan

Details

Specification section
31 20 00
Type
Work plan
Priority
Normal
Description
Specification 31 20 00 Earth Moving, paragraph 1.06 C.1. Submit for approval no less than 30 days before excavation; prepared by an Alaska-registered PE per OSHA 29 CFR 1926 Subpart P, including AHA, protective systems, egress, rescue plan, soil classification, shoring method, excavated soil management, digging permits; no mobilization of excavation equipment without approval, and revisions need 5 days for approval.