629 Excavation and trenching plan
Details
- Specification section
- 31 20 00
- Type
- Work plan
- Priority
- Normal
- Description
- Specification 31 20 00 Earth Moving, paragraph 1.06 C.1. Submit for approval no less than 30 days before excavation; prepared by an Alaska-registered PE per OSHA 29 CFR 1926 Subpart P, including AHA, protective systems, egress, rescue plan, soil classification, shoring method, excavated soil management, digging permits; no mobilization of excavation equipment without approval, and revisions need 5 days for approval.