281 HVAC start-up, testing, commissioning, and demonstration plans
Details
- Specification section
- 23 01 00
- Type
- Work plan
- Priority
- Normal
- Description
- Specification 23 01 00 General Mechanical Requirements, paragraph 1.08 C. Submit mechanical HVAC system start-up, testing, commissioning, and demonstration plans; 3.04 B requires complete plans 30 days prior to the scheduled test, startup, or demonstration date, identifying each system and piece of equipment. During construction.