281 HVAC start-up, testing, commissioning, and demonstration plans

Details

Specification section
23 01 00
Type
Work plan
Priority
Normal
Description
Specification 23 01 00 General Mechanical Requirements, paragraph 1.08 C. Submit mechanical HVAC system start-up, testing, commissioning, and demonstration plans; 3.04 B requires complete plans 30 days prior to the scheduled test, startup, or demonstration date, identifying each system and piece of equipment. During construction.