52 CPM reports (activity, logic, and total float reports)

Details

Specification section
01 32 00
Type
Schedule
Priority
Normal
Description
Specification 01 32 00 Construction Progress Documentation, paragraph 1.03 D. Concurrent with the CPM schedule, submit an Activity Report, Logic Report, and Total Float Report showing activity number, description, original and remaining duration, early/late start and finish, and total float; the initial issue also includes the tabulated reports of 2.03 F.