CBY Airport Water Extension

Submittal 662

HDD bore plan (methodology for each crossing)
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
33 05 23.13
Type
Work plan
Status
Not yet submitted

Description

Specification 33 05 23.13 Horizontal Directional Drilling, paragraph 1.05 C. At least one week prior to scheduled work submit the complete methodology specific to each crossing: work site drawing, equipment specifications, pilot hole size, pre-reams, pipe handling, tracking system, pipe sections, minimum pipe elevation, entry/exit angles, bending radii, weak link, anticipated soils and contingency plan; Engineer approval required before work (1.05 J).

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History

Printed Oct 12, 2026, 8:58 AM by VisitorWorkhorse · Hesiod Holdings