662 HDD bore plan (methodology for each crossing)
Details
- Specification section
- 33 05 23.13
- Type
- Work plan
- Priority
- Normal
- Description
- Specification 33 05 23.13 Horizontal Directional Drilling, paragraph 1.05 C. At least one week prior to scheduled work submit the complete methodology specific to each crossing: work site drawing, equipment specifications, pilot hole size, pre-reams, pipe handling, tracking system, pipe sections, minimum pipe elevation, entry/exit angles, bending radii, weak link, anticipated soils and contingency plan; Engineer approval required before work (1.05 J).