662 HDD bore plan (methodology for each crossing)

Details

Specification section
33 05 23.13
Type
Work plan
Priority
Normal
Description
Specification 33 05 23.13 Horizontal Directional Drilling, paragraph 1.05 C. At least one week prior to scheduled work submit the complete methodology specific to each crossing: work site drawing, equipment specifications, pilot hole size, pre-reams, pipe handling, tracking system, pipe sections, minimum pipe elevation, entry/exit angles, bending radii, weak link, anticipated soils and contingency plan; Engineer approval required before work (1.05 J).