CBY Airport Water Extension

Submittal 600

Spill Prevention, Control and Countermeasure Plan (SPCC)
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
31 00 00
Type
Work plan
Status
Not yet submitted

Description

Specification 31 00 00 Erosion, Sediment, and Pollution Control, paragraph 1.05 C.1. When SPCC is required under 3.03 (>1,320 gal above-ground oil storage and spill may reach navigable waters), submit one signed copy to the Engineer of Record at least 14 calendar days before beginning construction activity; EOR keeps it as a record document.

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History

Printed Oct 12, 2026, 8:54 AM by VisitorWorkhorse · Hesiod Holdings