Submittal 600
Spill Prevention, Control and Countermeasure Plan (SPCC)
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
- Specification section
- 31 00 00
- Type
- Work plan
- Status
- Not yet submitted
Description
Specification 31 00 00 Erosion, Sediment, and Pollution Control, paragraph 1.05 C.1. When SPCC is required under 3.03 (>1,320 gal above-ground oil storage and spill may reach navigable waters), submit one signed copy to the Engineer of Record at least 14 calendar days before beginning construction activity; EOR keeps it as a record document.
Disposition
☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only