CBY Airport Water Extension

Submittal 56

Construction schedule, initial (cost- and resource-loaded CPM)
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
01 32 00
Type
Schedule
Status
Not yet submitted

Description

Specification 01 32 00 Construction Progress Documentation, paragraph 2.03 C. Prepare a cost- and resource-loaded, time-scaled CPM network (AON format, one-workday units, no activity over 20 days, procurement activities for long-lead items) submitted so it can be accepted no later than 10 days after the Notice of Award date, with a working electronic copy labeled initial or updated (1.03 C.1).

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only