56 Construction schedule, initial (cost- and resource-loaded CPM)
Details
- Specification section
- 01 32 00
- Type
- Schedule
- Priority
- Normal
- Description
- Specification 01 32 00 Construction Progress Documentation, paragraph 2.03 C. Prepare a cost- and resource-loaded, time-scaled CPM network (AON format, one-workday units, no activity over 20 days, procurement activities for long-lead items) submitted so it can be accepted no later than 10 days after the Notice of Award date, with a working electronic copy labeled initial or updated (1.03 C.1).