CBY Airport Water Extension

Submittal 413

Grounding system field test and inspection reports
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
26 05 26
Type
Test report
Status
Not yet submitted

Description

Specification 26 05 26 Grounding and Bonding for Electrical Systems, paragraph 1.03 B. Field quality-control reports (listed under Action Submittals); per 3.05 E collect, assemble, and submit test and inspection reports, reporting measured ground resistances exceeding 10 ohms for systems 500 kVA and less; tests are witnessed by Engineer and performed by fall-of-potential method per IEEE 81. During construction.

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History