CBY Airport Water Extension

Submittal 712

Culvert field quality-control and backfill density reports
CBY Airport Water Extension
Project I0297.24002
Airport Road, Yakutat, Alaska 99689
Owner: City and Borough of Yakutat
Engineer: RESPEC
Specification section
33 41 00
Type
Test report
Status
Not yet submitted

Description

Specification 33 41 00 Storm Utility Drainage Piping, paragraph 1.06 B. Field quality-control reports; field densities on each culvert installation, one at the spring line and one per each foot of trench backfill above the top of pipe (3.06 A), plus interior inspection after 12 inches of backfill and at project completion (3.05 A). During construction.

Disposition

☐ Approved☐ Approved as noted☐ Revise and resubmit☐ Rejected☐ For record only

History

Printed Oct 12, 2026, 8:55 AM by VisitorWorkhorse · Hesiod Holdings