477 Panelboard infrared scan certified report

Details

Specification section
26 24 16
Type
Test report
Priority
Normal
Description
Specification 26 24 16 Panelboards, paragraph 3.04 B.3. After Substantial Completion but not more than 60 days after Final Acceptance perform infrared scan of each panelboard; 3.04 D requires a certified report identifying panelboards and describing scanning results with comparison of two scans, deficiencies, remedial action, and post-remedy observations; provide device calibration record. Closeout.

Files

No files attached.