Submittals
← Submittals

62 Contractor's Quality-Control Plan

Details

Specification section
01 40 00
Type
Work plan
Priority
Normal
Description
Specification 01 40 00 Quality Requirements, paragraph 1.06 A. Submit within 10 days of Notice to Proceed and not less than five days before the preconstruction conference, identifying QA/QC personnel, procedures, controls, tests, records and forms, the submittal review procedure, and a comprehensive schedule of Work requiring testing or inspection (1.05 A, 1.06 B, C, D).

Files

No files attached.

Drawings and specifications

History

Append-only

No history yet.