545 Generator infrared scan certified report

Details

Specification section
26 32 13.13
Type
Test report
Priority
Normal
Description
Specification 26 32 13.13 Diesel-Engine-Driven Generator Sets, paragraph 3.05 K.2. After Substantial Completion but not more than 60 days after final acceptance perform infrared scan of each power termination and bus connection at maximum load; certified report identifies terminations checked, scanning results, deficiencies, remedial action, and post-remedy observations; provide device calibration record. Closeout.

Files

No files attached.

Drawings and specifications

History

Append-only

No history yet.