9 Payment bond
Details
- Specification section
- 00 13
- Type
- Certificate
- Priority
- Normal
- Description
- Specification 00 13 Standard General Conditions of the Construction Contract, paragraph Article 2.01 A. Deliver to Owner with the signed counterparts of the Agreement; amount at least equal to the Contract Price, on EJCDC C-615 (2018) form per SC-6.01, surety listed in Treasury Circular 570, with certified copy of attorney-in-fact authority (Article 6.01 A, C).