Current revision 0
Aug 18, 2025 · 354 KBIssued for bid, August 2025
Revisions
1 revision| Revision | Issued | Note | File | Uploaded |
|---|---|---|---|---|
| 0 Current | Aug 18, 2025 | Issued for bid, August 2025 | 40 60 00 rev 0.pdfBluebeam | Torgen Soderlund Oct 10, 2026, 10:00 PM |
Linked from
72 records- 749 American Iron and Steel (AIS) certificate
- 750 Build America, Buy America Act certificate
- 751 PCS submittal schedule for multiple submissions
- 752 PLC controllers and I/O modules product data
- 753 Operator interface terminal (HMI) product data
- 754 Gateways product data
- 755 Routers and network equipment product data
- 756 Control panel enclosures product data
- 757 Electrical power devices (DC power supplies and relays) product data
- 758 UPS units product data
- 759 Pressure transmitter product data
- 760 Temperature sensor and transmitter product data
- 761 Hydrostatic level sensor product data
- 762 Float level switch product data
- 763 Position limit switch product data
- 764 Control valves and actuators product data
- 765 PCS accessories product data
- 766 PCS software submittal
- 767 PLC program flow diagrams and subroutine outlines
- 768 Instrumentation list and written sequence of operation
- 769 PCS equipment arrangement and mounting detail drawings
- 770 PCS control panel shop drawings
- 771 PCS electrical power riser diagram
- 772 Monitoring and control signal diagrams (point-to-point wiring)
- 773 HMI color graphic screen submittal
- 774 PCS system description
- 775 Documentation bibliography with preliminary testing and training descriptions
- 776 PCS delegated design documentation and calculations
- 777 Control valve and actuator schedule and sizing calculations
- 778 PCS coordination drawings
- 779 Systems Provider qualification data
- 780 PCS manufacturer qualification data
- 781 Testing agency qualification data
- 782 Source quality-control reports
- 783 Field quality-control reports
- 784 Sample warranty
- 785 PCS operation and maintenance data
- 786 PCS project record drawings (as-built shop drawings)
- 787 Final testing and commissioning reports and checklists
- 788 Custom PLC and HMI program documentation
- 789 Backup media of graphics, programs, and databases
- 790 Recommended spare parts list
- 791 Original-issue copies of furnished software
- 792 Licenses, guarantees, and warranty documents
- 793 Owner training materials
- 794 PLC software licensing in Owner's name
- 795 Four-year recommended parts list
- 796 Post-warranty one-year parts
- 797 Extra stock spare parts
- 798 UL 508A panel shop certification
- 799 Manufacturer's backing letter
- 800 PCS two-year special warranty
- 801 As-built schematics and wiring diagrams in each enclosure
- 802 Pre-installation examination report
- 803 Welder certificates
- 804 Network naming and addressing scheme
- 805 Wire and cable continuity and megger test results
- 806 NETA ATS inspection and test certification
- 807 Field instrument calibration procedures
- 808 Instrument calibration records
- 809 I/O control loop test report
- 810 Completed validation pretest checklist
- 811 PCS validation test plan and pretest checklist
- 812 PCS validation test report
- 813 Written request for PCS final review
- 814 Estimated cost of subsequent final reviews
- 815 Witnessed PCS final review demonstration (site acceptance)
- 816 PCS maintenance service agreement
- 817 Software service agreement
- 818 PCS training schedule
- 819 PCS training sign-in sheets
- 820 PCS training outline
Details
- Folder
- Specifications
- Section number
- 40 60 00
- Title
- Process Control System
- Library number
- DOC-0222
- Current revision
- 0
- Issued
- Aug 18, 2025
- Last updated
- Oct 10, 2026, 10:00 PM
Text
50 pages are searchable. The search reads the current revision.
History
Append-only- Torgen Soderlund (Contractor) · Added to the library at revision 0Oct 10, 2026, 10:00 PMIssued for bid, August 2025